Network Rail is taking immediate action to improve planning and delivery of rail enhancements

16 October 2015

Content archived on 19 April 2024

Archive date
02 July 2021
Body

Network Rail committed to deliver a challenging £13bn enhancements portfolio to improve performance and capacity on Britain's railways, in its current funding period between 2014-2019. In November 2014, ORR raised concerns about project deliverability and cost increases, and after a significant number of milestones were missed, launched an investigation in March 2015 to understand the reasons for enhancements going wrong.

ORR's investigation found systemic weaknesses in Network Rail's handling of its enhancement programme including poor processes for setting initial project requirements, no defined framework for managing complex programmes, a lack of portfolio management capability and low productivity. Together these issues have resulted in significant underestimates of project timescales, and impacted on operational performance and costs.

In response to ORR's investigation findings, Network Rail has worked with the regulator to identify and address its weaknesses through the development of an enhancement improvement plan. The plan will drive improvements in the way Network Rail manages its relationships with project sponsors, ensure safety is considered at a design stage, and reform how costs and risks are estimated, alongside changes in project governance, deliverability assessment and monitoring.

ORR will hold Network Rail to account for delivering the improvements needed, ensuring the plan is fit for purpose and put into practice. While it will be a significant and long-term challenge for the company to integrate and embed the improvements into business as usual, they are essential to protect the investment which is being funded by taxpayers, passengers and freight customers. 

ORR chief executive Richard Price said:

Network Rail has been entrusted with billions of pounds to modernise Britain's rail network. ORR has been closely monitoring the company's progress during the first year of the current funding period, and has found evidence of weaknesses in Network Rail's capability to develop and deliver major infrastructure enhancement projects.
Network Rail's response to our investigation findings has been positive and collaborative. We welcome its enhancement improvement plan, which requires significant changes to the company's processes, systems, culture and capability. ORR is now closely monitoring Network Rail's implementation of the necessary improvements, as they are fundamental to ensuring delivery of enhancements on time and budget for passengers and customers.

Notes to editors

  • The Office of Rail and Road is the independent economic and safety rail regulator and the independent strategic roads monitor for England. 
  • Follow the Office of Rail and Road on Twitter @railregulation for latest news data and announcements on the rail industry and @highwaysmonitor to keep updated on ORR's strategic road monitoring work. 
  • Further information on ORR's investigation and evidence is available online at: https://orr.gov.uk/what-and-how-we-regulate/regulation-of-network-rail/enforcement/enforcement-relating-to-enhancements 
  • Following an investigation, ORR's Board determined Network Rail is in breach of its licence for failing to adequately plan and deliver its enhancements programme. However, the regulator is content that the company's response and its implementation of an enhancement improvement plan will substantially improve its ability to deliver the extensive enhancements portfolio by 2019. 
  • In the current circumstances, ORR has determined that a financial penalty against Network Rail is not appropriate as it would not further incentivise improvements and it is more important that the company's financial resources are used to deliver the improvements to which it is committed. 
  • ORR has also today published its assessment of Network Rail's efficiency and financial performance for 2014-2015, the first year of control period 5 (CP5) which runs from April 2014 to March 2019. https://orr.gov.uk/news-and-media/email-alerts/2015/orr-publishes-its-assessment-of-network-rails-efficiency-and-financial-performance-for-2014-15